Long Running Functional Tests
These are the few notes I took from the "long running functional tests" discussions.
Problems
- Complete features take 1 day
- Functional test takes 15 hours
Alternatives, Risks, and Trade-offs
- Parallel testing vs. pipelined testing
- Compile
- Fast unit tests
- Slow unit tests
- Functional tests
- Incremental feedback during test runs
- Show failures sooner, but
- Does not typically lead to stopping the tests because we want to know all the results from that set of code